Control View Readout Playback Time / Remaining Cue Time

5/12/2024

Hello
I'm new to Vertex so sorry for a probably basic question. 

How do I display Values in Control Views? So let's say i want to basic display the current time of Sequence1. 

My guess:
> Adding a Label
> Caption Source sth like Playback1.CurrentShowCueRuntime

But without any success. I searched in the manual and was looking for a scripting / control view reference - maybe someone can throw light on that topic. ;)

Best and have a nice day
Samuel

Jan Huewel 5/13/2024

Hi your approach is correct
add a label
then select PME1->Playback1 in the Project explorer -> then go to the info tab in the inspector and drag drop the remaining timecode onto the label and assign its value to its source property.
if that does not help simply send an email to support@ioversal.com