5/12/2024
Hello I'm new to Vertex so sorry for a probably basic question. How do I display Values in Control Views? So let's say i want to basic display the current time of Sequence1. My guess: > Adding a Label > Caption Source sth like Playback1.CurrentShowCueRuntime But without any success. I searched in the manual and was looking for a scripting / control view reference - maybe someone can throw light on that topic. ;) Best and have a nice day Samuel
Jan Huewel 5/13/2024
Hi your approach is correct add a label then select PME1->Playback1 in the Project explorer -> then go to the info tab in the inspector and drag drop the remaining timecode onto the label and assign its value to its source property. if that does not help simply send an email to support@ioversal.com